WRRDA 2014, Section 1002 - Consolidation of Studies

This section amends Section 905 of the Water Resources and Development Act (WRDA) 1986 to establish a single phase cost-shared study process and that for each feasibility study undertaken, the district engineer will develop a detailed study schedule and to notify the non-federal interests.  The reporting requirement is applicable to active studies that received investigations funding from October 1, 2009, to June 10, 2014, or within 90 days of signing Federal Cost Sharing Agreements for studies initiated after June 10, 2014.

A copy of the letters and an overview of study schedule milestones are posted below. 

* - Tentatively scheduled dates, subject to change

Feasibility Study Release of Draft Feasibility Report  District Submits Final Feasibility Report   MSC Transmits Final Feasibility Report Signed Chief's
Report 
Louisville Metro Flood Protection System Reconstruction Nov. 15, 2019 July 2, 2020 July 7, 2020 Oct. 27, 2020

Three Forks of Beargrass Creek

April 24, 2021* Feb. 4, 2022* April 15, 2022* Aug. 5, 2022*